Germantown Avenue Bridge over Wissahickon
Creek
Reprinted from the November issue
of Modern Steel
Construction
The Germantown Avenue Bridge over Wissahickon
Creek in Philadelphia is a three span curved steel girder bridge
that was designed to safely replace a falling nine span straight
bridge. The location of the old bridge forced a hazardous curve,
allowing a maximum speed of only 15 mph.
In
1997, several undermined piers cracked and, after emergency
repairs, vehicular traffic was restricted to one-way next to
the downstream edge of the deck. Structurally, the bridge was
rated “poor” even before the piers cracked. Collapse
or removal of the sidewalk overhangs required the addition of
traffic barriers that restricted roadway width and further reduced
safe operating speed.
A new, horizontally curved roadway alignment replaced the existing
sharp bend to improve roadway safety. The resulting baseline
radius of about 488’ required the curved superstructure.
The 14,000 cfs flow of Wissahickon Creek was also severely
constricted by this bridge’s eight original stone piers,
which created narrow hydraulic openings of approximately 18’.
Upstream flooding occurred when one or more of the spans clogged
with debris. Increased stream flow velocity in the remaining
spans caused major scour beneath the foundations, which required
periodic repairs.
The number of spans for the new bridge was limited to three
to improve the stream flow underneath, and new abutments were
placed beyond the existing abutments. The combination of the
curved alignment and the positioning of the piers and abutments
parallel to the stream caused skew angles as low as 50 degrees
between the bearing lines and baseline. A relatively shallow
superstructure was proposed to keep the bridge above the 100-year
storm water surface elevation.
A refined method of analysis was performed on the curved steel
girders and radial positioned diaphragms to determine design
forces. Initial results indicated very large diaphragm forces.
Rather than proposing massive diaphragms, the engineers removed
the diaphragms located closest to the piers and abutments. Re-analysis
results indicated lower diaphragm forces while still providing
adequate lateral bracing for the girder compression flanges.
Aesthetic Considerations
Two separate superstructures were designed for sidewalks. The
upstream sidewalk and roadway lanes were placed on a constant
width curved deck. The downstream sidewalk was located on a
variable width chorded deck with a curved upstream edge to match
the downstream edge of the vehicular deck for two of the three
spans. The engineers were able to successfully design each structure,
given the significant curved beam requirements, through the
use of fabricated steel to support each deck.
The owners wanted a pedestrian superstructure deck that was
durable, aesthetically pleasing, and capable of being quickly
replaced if damaged. Wood planking over steel grid flooring
met these requirements. The steel grid was easily attached to
the supporting steel beams. The wood deck was assembled in panels
and bolted to the steel grid, which allowed rapid partial replacement
of deck areas if needed.
The owners also wanted building materials that would look pleasing
but require minimal maintenance. All visible structural steel
was protected with a three-coat epoxy paint system pigmented
to match the surrounding green foliage. Non-visible structural
steel was galvanized.
All cast in place concrete was textured or stone-lined and
pigmented.
Excessive lateral movement was detected when an external horizontal
movement was introduced after erection of the steel girders
for the pedestrian bridge. It was believed that the installation
of the steel grid and wood deck would stabilize the structure,
but methods to reduce the movement were also considered as a
precaution. The designers suggested that a “soft-tie,”
similar to a steering strut on an automobile, be placed between
the outside vehicular bridge steel girder and the inside pedestrian
bridge steel girder. The intent was to provide lateral restraint
to the pedestrian bridge without transmitting live load deflections
or vibrations from the vehicular bridge into the pedestrian
bridge. A detail using steel rods and fabric pad washers and
bushings was developed. The concept was installed before the
steel grid and wood deck were attached to the girders. After
completion, the pedestrian bridge exhibited no perceptible lateral
movement due to external force and no perceptible vibration
during car or truck passage on the vehicular bridge.
The engineers elected to replicate the original bridge’s
railing. Although both of the original railings had been lost
during failure of the sidewalks, the city had detailed drawings
of them. These drawings enabled a copy for use on the new structure.
A shorter railing was used on top of the shaped safety barriers
to protect bicycle riders from falling.
Realignment of the roadway necessitated the removal of one
of two driveways to a nearby college. The college requested
that the remaining entrance be widened and improved with a new
traffic signal. The wider entrance would allow construction
of a future guard house between the incoming and outgoing lanes.
The existing entrance was flanked by a 15’-long by 5’-wide
by 6’-tall pilaster on each side. The engineers proposed
that one of the pilasters be carefully disassembled and reconstructed
to provide the wider entrance. However, after excavation around
the pilaster was completed, it was decided to roll the entire
pilaster into its proposed location. This was performed successfully
and the architectural integrity of the structure was maintained.
The new roadway was designed for a 35 mph travel speed. Lane
widths were reduced to only 11’ to encourage slower travel
speeds. Super elevation was initiated to two percent, and shoulder
and bikeway rumble strips confine motorists within the cartway.
The bridge provides hydraulic openings of at least 75’.
A separate, adjacent, downstream structure provides a wider,
wood-decked pedestrian crossing. Use of real and formed stone
surfaces on parapets, traffic barriers, and substructures helps
integrate the bridge into its surroundings.